Q: Can you please confirm which IPMVP Option most closely aligns with the following approach for both single-ECM and multi-ECM projects?
A: Overall – an IPMVP Option approach consists of both a baseline method and a corresponding post-EEM (reporting period) measurement method.
Q: Perform Baseline Energy Metering - Energy meters are installed to the circuits feeding power to the addressed equipment/systems to isolate those systems from the rest of the building and capture pre-ECM(s) energy use. The baseline metering period for a given project is determined based on site local weather variations, the operating characteristics of the addressed equipment/system, and the proposed scope of work. These meters will remain installed during implementation of the ECMs.
A: [i]As stated, this Baseline approach seems to be focused on isolation of the retrofit/EEM with the installed meters. Given this information, this baseline approach for retrofit isolation with potential of all parameter measurement via the electric meters, would align with an Option B method of baseline determination.
[*][/i] [b][/b]
Q: Generate the Energy Baseline - The subhourly baseline period energy meter data in concert with coincident local weather data for the baseline period are used to derive the weather and time-of-week normalized baseline model for isolated systems at the building.
A: Same as above – appears to be stating retrofit isolation via energy meters – Option B – again, assuming the metering is capturing all parameters required for energy consumption and demand.
Q: Perform Post-ECM(s) Energy Metering - The energy meters that were installed for the baseline energy metering will be used to monitor and track the energy use of the addressed equipment/systems post-implementation of the ECMs. The post-ECM(s) energy metering period is one calendar year after the owner's acceptance of the implemented ECMs.
A: Same as above – retrofit isolation via meters which are capturing total retrofit energy use (all parameters) – used during reporting period for EEM savings determination – Option B.
Q: Verify Project Performance - The performance of the project in aggregate (i.e., all ECMs combined) is verified by comparing the actual annual energy savings to the estimated annual energy savings.